Constitution of India — Article 226 — Article 300-A — Writ of Mandamus — High-tension transmission towers — Alleged deviation from approved re-location plan — Obstruction to irrigation — Apprehension without material proof — No writ interference.
Electricity transmission — Licensees — Laying and shifting of transmission lines for National Highway project — Public safety and public interest — Alternative alignment — Irrigation channel not affected.
Held:
When competent authorities categorically state that transmission towers and lines are not being laid through irrigation channels and a proper alternative alignment is finalized, a grievance based solely on apprehension does not warrant issuance of writ under Article 226.
(Paras 6 to 8)
FACTS (As emerging from the Judgment)
-
The petitioners claimed ownership over agricultural lands situated in Pennepalli Village, Pellakuru Mandal, comprising:
-
Ac.0-70 cents in Sy.No.91-1
-
Ac.1-01 cents in Sy.No.96-11 (LPM No.435)
-
Ac.0-39 cents in Sy.Nos.96-8A & 96-9A (LPM No.465)
acquired through registered sale deeds and under cultivation. (Para 3)
-
-
The petitioners alleged that respondent Nos.2 to 5 were attempting to lay two high-tension transmission towers (132 KV and 220 KV) along with electrical lines on their agricultural lands, which would obstruct irrigation and violate Article 300-A of the Constitution. (Para 3)
-
The petitioners further alleged deviation from the approved re-location plan and sought removal of existing towers and shifting them to Sy.No.96-9A1 (LPM No.464) of Pennepalli Village. (Relief clause)
RELIEF SOUGHT
Issuance of a writ of mandamus declaring deviation from the approved re-location plan as illegal and unconstitutional, restraining extension of tower bases in petitioners’ lands, and directing removal and shifting of existing high-tension towers as per the approved re-location plan. (Para 1)
SUBMISSIONS OF THE PARTIES
Petitioners
The petitioners contended that:
-
The erection and extension of tower bases would obstruct irrigation.
-
Courts have consistently held that natural water courses and irrigation channels cannot be obstructed.
-
Deviation from approved re-location plan is illegal and violative of property rights under Article 300-A. (Paras 3 & 4)
Respondents
The learned Standing Counsel submitted that:
-
The 220 KV Manubolu–Sullurpeta-1 SC line (Loc. Nos.169 to 170) is being laid as part of the six-lane NH-71 project from Renigunta to Naidupeta under Hybrid Annuity Mode.
-
Detailed surveys were conducted considering technical feasibility and public safety.
-
The proposed electrical lines are not being laid through any irrigation channel.
-
A proper and suitable alignment has been finalized avoiding obstruction to irrigation. (Paras 5 to 7)
ISSUE FOR CONSIDERATION
Whether the petitioners were entitled to writ relief restraining erection or extension of high-tension transmission towers on the allegation of deviation from re-location plan and obstruction to irrigation.
ANALYSIS & REASONING OF THE COURT
-
The Court considered the petitioners’ claim regarding obstruction to irrigation and alleged deviation from the approved re-location plan. (Para 3)
-
The Court took note of the respondents’ explanation that:
-
The work is undertaken by competent licensees under Rule 3 of the Act.
-
The shifting and laying of transmission lines is in public interest and public safety.
-
The alignment has been finalized in such a manner that no irrigation channel is affected. (Paras 6 & 7)
-
-
The Court specifically recorded the clear and categorical submission of the respondents that the electrical lines are not constructed through the irrigation channel, contrary to the petitioners’ allegation. (Para 7)
-
In view of these categorical statements, the Court held that the petitioners’ grievance was only an apprehension without supporting material. (Para 8)
-
Consequently, the Court found that no specific directions or interference were warranted under Article 226 of the Constitution. (Para 8)
FINAL ORDER / DIRECTIONS
-
The writ petition was disposed of. (Para 8)
-
No order as to costs.
-
Pending miscellaneous applications, if any, were ordered to stand closed.
RATIO DECIDENDI
A writ court will not interfere with infrastructure or transmission works undertaken by competent authorities in public interest when there is a categorical assurance that irrigation channels will not be obstructed and the grievance raised is based merely on apprehension without substantiating evidence
No comments:
Post a Comment